Monday, November 14, 2011

Pre Drywall meeting on Thursday, 17 November.

 We have finalized our pre drywall meeting on November 17 in the afternoon. And in the morning we are taking our own home inspector to do the inspection. I have my own list of questions/concerns to ask to our home inspector and to the PM. That's why we have kept whopping 5 hrs of time margin between inspection and pre drywall meeting.  It's going to be a busy day!! But I hope everything will go smoothly.  Will post the details of our pre drywall meeting for sure.

This morning we had a meeting with Trinity Rep. at out lot to finalize the locations for duel ports, keypads, motion detectors etc etc. It went for about an hour.

So in all lot of action is going on in the house.
  • The HVAC system is in  it's place. 
  • Plumbing crew was working on rest of the plumbing. So plumbing will be finished by the end of the day. 
  • Trinity wiring crew is going to finish their job today itself. 
  • Electrical wiring will get done may be tomorrow. (?)
  • our garage door got installed on Friday. 
  • Bath tubs and shower pan is installed in the bathrooms. 
We have garage door !!

Add caption
 Can't wait to get (tentative) official closing date after the pre drywall meeting. And can't wait to lock the rate. Keeping my fingers crossed and hope high on getting the interest rate below 4 % 
Almost can't believe how time flies. It feels like yesterday that we signed the contract and now we are already talking rate locking...  and closing.... and furniture.... and future projects... !!
I can surely say that I am absolutely enjoying the home building process  although I have my anxiety attacks from time to time as to how our house is going to turn out ? But yes we ARE having the time of our lives !!!!